Reindustrialisation: opening a factory is one thing, ramping it up is another

30 minutes ago
5 min read

France’s reindustrialisation drive is often measured by the number of new sites being opened. Once a factory is inaugurated, however, another decisive phase begins: reaching the right production volumes, meeting delivery targets, and stabilising quality and costs.


Industrial production line in ramp-up phase


The momentum is clearly there. By the end of September 2026, Bpifrance recorded 202 new industrial site openings in France, compared to 187 during the same period in 2025. Of these, 130 involved SMEs and mid-sized companies. The overall balance remained positive, with 202 openings and 174 closures.

 

And the trend is continuing. On November 10th, France 2030 announced another 13 new projects supported by the "First Factory" scheme, in sectors as diverse as chemicals, aeronautics, robotics, health and industry 4.0. Since its launch in 2022, this program has already supported more than 100 industrial projects.

 

Once the buildings are ready and the equipment is installed, the real industrialisation phase begins. The company must be able to transform theoretical capacity into reliable, repeatable production capable of progressively reaching the planned output levels. And that's often where the difficulties begin…



A production line reaches its target rate in stages


Starting up new equipment usually opens a phase of adjustment and learning. Teams must stabilize processes, adjust machines, train themselves, address recurring defects, improve workflows, and learn to manage unforeseen events.


Bpifrance also points out that new equipment requires a ramp-up and learning phase , both for operational teams and support functions, before reaching its target performance level.


The first few months of a new site therefore need to be managed against realistic, progressive objectives. Accelerating too quickly can increase scrap, rework, breakdowns and pressure on teams, while also creating delays further down the process.


The ramp-up must therefore be considered primarily as a fully-fledged industrial project , with, like any project, its stages, indicators and unavoidable trade-offs.



Industrialisation means making production repeatable


Industrial production line in ramp-up phase

The shift from small batches to larger volumes profoundly changes production conditions.


Thus, a method heavily reliant on the expertise of a few specialists can become fragile. Manual control, suitable for small batches, can become a bottleneck. An insufficiently standardized process can also generate more variability as volumes increase.


Scaling up therefore requires the company to examine several points:


  • Are the processes sufficiently stabilized?

  • Are the production standards clear?

  • Do the cycle times correspond to the initial assumptions?

  • Have the causes of poor quality been identified?

  • Is the maintenance system adequately sized for the new production rates?

  • Do the indicators allow us to anticipate a drift rather than simply observing it?


The challenge is to prove that the product can be manufactured repeatably, with the expected level of quality, cost, and delivery time . Successful industrialization therefore requires production that is sufficiently stable and predictable to sustainably absorb higher volumes.


READ ALSO: Structuring processes and quality management



Ramp-up also depends on the teams


Beyond the means of production to be deployed to ensure the ramp-up, it is obviously also necessary to have the skills to operate them.


However, French industry continues to face significant shortages in certain professions. The 2026-2029 national roadmap for industrial employment specifically identifies needs in maintenance, automation, robotics, process engineering, and professions related to energy transitions.


Ramp-up production therefore requires not only recruitment but also the rapid integration of new employees, the transfer of expertise, and the establishment of a solid middle management team. A new site can sometimes bring together, within a few months, teams that have little prior experience working together.


Local management plays a major role here: distributing responsibilities, establishing management routines, transmitting standards and creating shared ways of working.


Equipment gives the site its production capacity. The organization and its people make that capacity sustainable.



Ramp-up also takes place beyond the factory walls


Increased production inevitably leads to a rise in the need for materials, components, services, and logistical capacity. However, achieving the projected volumes requires that these materials, components, and services be available at the right pace.


Suppliers and subcontractors must therefore also be able to absorb the increased workload. A critical component that is not available in sufficient quantities or a partner that is already overloaded can slow down the entire site.


The company must then identify its critical dependencies, secure supplier capacities and adjust stock levels or alternative solutions as needed.


The same logic applies downstream. Storage, shipping and transport must also keep pace with the increase in volumes.


The performance of the new site therefore depends on the ability of the entire chain to ramp up at the same pace.


READ ALSO: Securing your Supply Chain during a ramp-up


Management must be able to make decisions quickly


Industrial production line in ramp-up phase

Launching a factory always creates numerous interdependencies. A recruitment delay can affect production. Insufficient production rates can impact customer deadlines. A quality issue may force a temporary slowdown. Supplier tensions can jeopardize the planned schedule…


The company must therefore organize a governance structure capable of quickly transforming this information into decisions.


  • What indicators should we monitor each week?

  • What problems require an immediate decision?

  • Who can change the production schedule?

  • When should volume be prioritized, and when should we deliberately slow down to stabilize the process?


This phase requires an operational management team close to the field , capable of coordinating the functions involved, arbitrating priorities and monitoring the execution of decisions taken.



The Interim Manager can lead the ramp-up phase


A small or medium-sized enterprise (SME) or a mid-sized company (ETI) opening a new site or significantly increasing its capacity may need, for several months, a highly experienced manager capable of leading this ramp-up phase. Interim management is particularly well-suited to this temporary and highly operational need.


Depending on the context, an Interim Manager in Industrial Management, Operations Management, or Supply Chain can, in particular:


  • structure the ramp-up plan;

  • install the indicators and monitoring routines;

  • coordinate production, maintenance, quality, purchasing and Supply Chain;

  • identify the main bottlenecks;

  • secure critical suppliers;

  • to support the skills development of the teams;

  • clarify responsibilities;

  • arbitrating priorities when several difficulties arise simultaneously;

  • prepare an organization capable of functioning sustainably after his departure.


The value of an Interim Manager lies in combining substantial industrial experience with the ability to execute immediately.


The Interim Manager temporarily takes responsibility for a specific area, sets up the necessary methods, supports the teams and prepares the handover to a stabilized organization.


His intervention also allows the General Management to maintain availability for other issues related to the development of the new site: customers, investments, recruitment, partners or industrial strategy.



Industrial success begins after the inauguration


The increasing number of new site openings is a positive sign for French industry. The success of these investments will then be measured by their ability to achieve the planned production targets, with the expected levels of quality, delivery time, and profitability.


Reindustrialization thus relies on the entire implementation chain: financing, construction, equipment, recruitment, industrialization, supply chain, management and ramp-up.


It also plays out in this less visible but decisive step: transforming a new industrial capacity into a high-performing and sustainable production tool.



Are you opening a new site, increasing your capacity, or preparing for a ramp-up?

TOPS Ressources can rapidly deploy experienced Interim Managers in Industrial Management, Operations and Supply Chain to structure the ramp-up and support teams until the organisation is fully stabilised.





Sources:

Bpifrance — Industry Observatory, review of factory openings as of the end of September 2026

.

Directorate General for Enterprises — France 2030, 13 new “First Factory” projects, November 10, 2026.

 

Directorate General for Enterprises — National roadmap for attractiveness and employment in industry.

 

Bpifrance Conseil — Guide on TRS and ramping up new equipment.